Being one of the largest shopping centers to have been built in the Southern Hemisphere IES was extremely happy
when they were awarded the tender on this project. The mall sees more than 1.30 million visitors coming through
its doors per month.
|
| |
| Entire Shopping Centre |
| 125000 |
| 22000 |
| R 66 000 000 |
| 2001 |
| |
| |
| Central chilled water plant room. |
| Chilled water serving air handlers with ducted distribution. |
| General ventilation and dedicated smoke extraction ventilation installed. |
| |
| |
| Chillers- Carrier. |
| Cooling Towers- Sulzer. |
| Pumps- KSB |
| Air Handling Units - Viking, Trox, Apache. |
|
|
|
|